Article #511 Using Technology to Enable a 360-Solution to Manage, Monitor, Evaluate and Report the Performance of Retail Brands Expansion and Remodeling Programs and Projects – Step 4: Enforce Proactive Risk Management and Effective Issues Resolution

Retail brands’ expansion and remodeling projects are no different than other types of projects in terms that they are based on many assumptions to address the many unknowns. Therefore, enabling a proactive risk management process coupled with an effective issues resolution process for risks that have occurred is vital.

Using the same Project Management Information System (PMIS) platform being PMWeb, it is highly recommended that the entity responsible for managing the retail brands projects develop a comprehensive risk checklist to be used on all their expansion and remodeling projects. The risk checklist will include all possible risks that could encounter during the delivery of such projects. The risks will be grouped into categories that will be aligned with the risk breakdown structure. The risk register will be updated with new and emerging risks to ensure that they cover all possible causes of risks.

D62.png

PMWeb visual custom form builder will be used to create a comprehensive risk checklist that will cover all risk categories. The custom form header will include details on the project, the project phase where the risk checklist analysis was done, the status of the risk checklist which will be by the assigned workflow, and any other general information needed for the checklist.

Nevertheless, what is important to have is the possible risks within each risk category. Those could include Organizational and Project Management Risks, Contract Acquisition Risks, Technical Risks, Lands and Damages, Regulatory and Environmental Risks, Construction Risks, Estimate and Schedule Risks, and External Risks.

For each risk identified under one of those categories, the checklist will include fields for pre-mitigation likelihood and impact scores, proposed risk response strategy to treat the risk, details of the risk mitigation action to be implemented, and the post-mitigation likelihood and impact scores. For the likelihood and impact score fields, a predefined list of values between “0” and “5” has been added. The value “0” will be used if this risk is not applicable for the current project or phase, while the values from “1” to “5” will be for the chances of occurrence and severity of impact. The value “1” will be for very low probability or impact and “5” for very high probability or impact.

511 1

In addition, PMWeb custom form builder was used to create the “Issue Resolution” form in the desired form and format to capture all needed details. Those could be the issue type, category, criticality, issue description, the issue raised by an issue owner, needed issue resolution date, and which project schedule activity does its first impact. The issue form will also include the fields for issue impact and severity which will automatically calculate issue severity. The form will also include fields for issue resolution actions and a description of the attached documents. In general, the form should be detailed to the level that eliminates ambiguities and miss-communication of the reported project issue.

511 2

A report will be created to capture the details of all raised issues and their status. The report will include visuals to the group and organize issues by type, priority, status, issued by, and other data fields that will help in monitoring and tracking the status of issues until they are fully resolved.

D10.png

About the Authorfounder

Bassam Samman, PMP, PSP, EVP, GPM is a Senior Project Management Consultant with 40-year service record providing project management, project controls services, and project management information systems to over 200 projects with a total value over the US $100 Billion. Those projects included Commercial, Residential, Education, and Healthcare Buildings and Infrastructure, Entertainment, Hospitality, and shopping malls, Oil and Gas Plants and Refineries, Telecommunication, and Information Technology projects. He is thoroughly experienced in complete project management including project management control systems, computerized project control software, claims analysis/prevention, risk analysis/management (contingency planning), design, supervision, training, and business development.

Bassam is a frequent speaker on topics relating to Project Management, Strategic Project Management, and Project Management Personal Skills. Over the past 40 years, he has lectured at more than 350 events and courses at different locations in the Middle East, North Africa, Europe, and South America. He has written more than 500 articles on project management and project management information systems that were featured in international and regional magazines and newspapers. He is a co-founder of the Project Management Institute- Arabian Gulf Chapter (PMI-AGC) and has served on its board of directors for more than 6 years. He is a certified Project Management Professional (PMP) from the Project Management Institute (PMI), a certified Planning and Scheduling Professional (PSP), and Earned Value Professional (EVP) from the Association for the Advancement of Cost Engineering (AACE) and Green Project Management (GPM).

Bassam holds a Masters in Engineering Administration (Construction Management) with Faculty Commendation, George Washington University, Washington, D.C., USA, Bachelor in Civil Engineering – Kuwait University, Kuwait and has attended many executive management programs at Harvard Business School, Boston, USA, and London Business School, London, UK.

 

Contact us