Article #143 Monitoring, Evaluating and Reporting Planned and Actual Resources Usage and Performance Efficiency During the Capital Project Engineering Phase

For Engineering Consultants, EPC Contractors, Design-Build Contractors, and other entities whose scope of work includes creating engineering deliverables such as drawings, specification among others, they always need to plan the needed resources to create those deliverables and capture the actual resource hours spent in creating them. They need this information to enable them to monitor, evaluate and report on any variances, the reasons that have caused those variances, and the actual performance efficiency achieved to date to enable them to implement the needed measures to improve the efficiency for the remaining scope of work to avoid resources overrun.

Using a Project Management Information System (PMIS) like PMWeb, Engineering Consultants, EPC Contractors, DB Contractors, and others can use PMWeb to plan the resources requirement for the complete project life cycle phases as well as the design engineering phase. In addition, PMWeb allows capturing the actual resource hours spent during the design phase to monitor, evaluate and report on resource usage variances. Further, if the earned value (EV) for engineering deliverables is also provided, then the organization can create a report to monitor, evaluate and report on resource performance efficiency.

Determining the Engineering Phase Resources Requirement

Usually, Oracle Primavera P6 or MS Project will be used to plan to determine and plan the resources requirements during the engineering phase. Activity will be created for each engineering phase deliverable with the option to detail the activities needed to complete a deliverable. Those activities will be resource-loaded with the needed resources and their manhours. The project schedule’s resources requirement will be leveled to the extent possible to avoid having resources overload. Upon completion of this analysis, the resources requirement report will become the basis for determining the needed resources to be booked during the engineering or design phase of the project.

export p6 resource assigments to Excel tutorial

Planning the Project Resources Requirements

Understanding that when booking the resources for the design and engineering phases, there will be periods that the resources could be under-utilized because of how the project was planned. PMWeb resources requirement module will be used to book the resources needed for the design phase. This will be similar to the resources’ availability levels defined in Oracle Primavera P6 and MS Project. The organization can create multiple resources requirement forms for each phase or engineering discipline instead of having a single requirement form. Each requirement form can be linked to the schedule summary activity, which was imported from Primavera P6 or MS Project to PMWeb, for the design phases as an overall, design stages or engineering disciplines.

It is highly recommended that the engineering resources used by PMWeb use the same resource codes used in P6 or MS Project although this is not a must requirement. The resources dictionary in PMWeb can be created to match the organization’s resources naming, codes, and values.

In addition, PMWeb allows using the Organization Chart module to create an organization chart to map the lines of authority between the project team members, that is resources, for the engineering design phase as an overall or even it can be specific for each discipline. There is no limit on the number of organization charts that can be created for a project.

Capturing Actual Resources Hours Spent Using Timesheets

As the design or engineering phase commences, the PMWeb timesheet module will be used to capture the actual resource hours spent against each deliverable which is an activity in the project’s detailed schedule. Those hours could be regular working hours, overtime hours, weekend hours, and/or holidays hours. A workflow will be assigned to the submission, review, and approval of the reported actual resource hours. The timesheet module will also allow capturing notes made by the project team about events that could have caused disruption, rework, or other reasons that could have resulted in spending additional manhours against the design deliverable.

Monitoring, Evaluating, and Reporting Actual Man-Hours Spent Against Planned

The actual resource hours captured from the PMWeb timesheet module and the planned resource hours from the resource requirements module will be the basis for creating a real-time dashboard to monitor, evaluate and report the professional services resources utilization. In other words, the organization would be interested to know if the booked resources for a discipline or a phase were equal to the number of actual resource hours consumed. The report will also show the total resource manhours variance per quarter.

To report the resources’ performance efficiency, the Planned Value (PV) of resource usage for each engineering deliverable activity as per the resource loaded schedule and the Earned Value (EV) for the same deliverable activity which will be calculated by multiplying the percent complete for each deliverable by the total resource hours allocated for the activity (BAC) will be needed. The percent complete for each deliverable will be calculated by the set progress weight percentages set for engineering deliverables. Of course, the Actual Quantity (AC) of resource hours spent will be also needed which is the actual hours captured in the PMWeb timesheets module.

Those values will be the basis for calculating earned value metrics which will include Cost Variance (CV) which is “EV – AC”, Schedule Variance (SV) which is “EV – PV”, Cost Performance Index (CPI) which is “EV/AC” and Schedule Performance Index (SPI) which is “EV/PV”.

 

About the Authorfounder

Bassam Samman, PMP, PSP, EVP, GPM is a Senior Project Management Consultant with more than 35-year service record providing project management and controls services to over 100 projects with a total value over the US $5 Billion. Those projects included Commercial, Residential, Education, and Healthcare Buildings and Infrastructure, Entertainment and Shopping Malls, Oil and Gas Plants and Refineries, Telecommunication, and Information Technology projects. He is thoroughly experienced in complete project management including project management control systems, computerized project control software, claims analysis/prevention, risk analysis/management (contingency planning), design, supervision, training, and business development.

Bassam is a frequent speaker on topics relating to Project Management, Strategic Project Management, and Project Management Personal Skills. Over the past 35 years, he has lectured at more than 350 events and courses at different locations in the Middle East, North Africa, Europe, and South America. He has written more than 250 articles on project management and project management information systems that were featured in international and regional magazines and newspapers. He is a co-founder of the Project Management Institute- Arabian Gulf Chapter (PMI-AGC) and has served on its board of directors for more than 6 years. He is a certified Project Management Professional (PMP) from the Project Management Institute (PMI), a certified Planning and Scheduling Professional (PSP), and Earned Value Professional (EVP) from the American Association of Cost Engineers (AACE) and Green Project Management (GPM).

Bassam holds a Masters in Engineering Administration (Construction Management) with Faculty Commendation, George Washington University, Washington, D.C., USA, Bachelor in Civil Engineering – Kuwait University, Kuwait and has attended many executive management programs at Harvard Business School, Boston, USA, and London Business School, London, UK.

 

Contact us